![]() |
![]() |
![]() |
|
NORWALK
FACILITIES CONSTRUCTION COMMISSION ACTIONS
|
|
Click
here for Minutes from March 1, 2006 Click here for Minutes from April 5, 2006 Click here for Minutes from May 3, 2006 Click here for Minutes from May 17, 2006 |
JULY 6, 2006
ATTENDANCE: Mayor Richard A. Moccia; Paul Arcario; Stuart Opdahl;
Nick Pacella; John Tobin; Doug Hempstead (5:45 p.m.);
Doug Sutton (5:45 p.m.)
STAFF: John Hawley, Gilbane; Amar Shamas, Gilbane; Ben Burdsall, Gilbane
OTHER:
CALL TO ORDER
Mayor Moccia called the meeting to order at 5:35 p.m.
MINUTES OF PREVIOUS MEETING (S)
June 7, 2006
** MR. PACELLA MOVED TO APPROVE THE MINUTES OF JUNE 7, 2006.
** MOTION PASSED UNANIMOUSLY.
Mayor Moccia said that he, Mr. Opdahl, Dr. Corda, and the lawyers have met
regarding the recent discussions to move the portables from Brien McMahon High
School to Jefferson School. It was agreed that the project will now go out on
a bid basis, and it will be brought back to the Facilities Commission for discussion
and review.
NORWALK SCHOOL PROJECTS
A. Brien McMahon High School/Center for Global Studies Improvement Project
1. Project update by John Hawley (Program Manager)
Mr. Hawley said that a temporary Certificate of Occupancy has been issued
for the Phase 3B areas. The last phase of the project should begin next week.
The next step will be to remove the portables, and then the construction of
the softball field can begin. The entire project will be substantially complete
by the end of July.
Mr. Hempstead and Mr. Sutton arrived at 5:45 p.m.
2. Review and approve the following change orders:
CCA #20196 $ 9,476.00 Increase GMP Misc additional masonry patching as required at various field conditions
BEA #20291 $ 3,925.00 CM Wood blocking at the bases of the boys
Contingency and girls room gym lockers
CCA #30006 $ 2,847.00 Increase GMP Added door and frame at roof access
door #2097A, per RFI #652
CCA #30016 ($3,702.00) Decrease GMP Credit to delete demo of the existing
chemistry building (bought twice)
CCA #30020 $ 3,584.00 Increase GMP Added exhaust fan in electrical room
1166, per RFI #685
CCA #30032 $ 5,125.00 Increase GMP Provide added metal wall panels and
flashings at field conditions
CCA #30040 $ 8,466.00 Increase GMP Provide added power feeds to fitness
room to power equip per FT sketch
CCA #30042 $ 2,005.00 Increase GMP Added bituminous walkway to tennis
courts per RFI #711
CCA #30043 $ 1,638.00 Increase GMP Added break metal soffits to clear piping
at phase 3B classroom windows
CCA #30044 $ 4,608.00 Increase GMP Added CMU and fireproofing at top of
fitness room wall per RFI #709
CCA #30045 $ 2,048.00 Increase GMP Provide furring and gyp board to cover
walls at stair 6 field conditions RFI #705
CCA #30046 ($ 320.00) Decrease GMP Provide spray intumescent fireproofing
in
lieu of CMU at cols per RFI #709
CCA #30036 $14,419.00 Increase GMP Provide exterior louvers at UV’s between
stairs 4 and 7, not shown on elevation
BEA #40036 $14,081.00 CM Provide ext louvers at UV’s between
Contingency stairs 4 and 7, not shown on elevation
Mr. Hawley explained that CCA #20196 is for cutting and patching, where existing
mechanicals, ductwork, and wall construction didn’t match the drawings. It was
needed in the gym areas and around the stairwells.
CCA #30040 was to provide independent power feeds to the fitness equipment that the Board of Education had received as a gift.
CCA #30036, and BEA #40036 are a split for an in-scope vs. out of scope change
for the mechanical contractor. Subsequent to submitting the large claim that
is currently being worked on, they noted that there are some louvers on the
exterior of the building that are not on certain drawings. They refuse to provide
the louvers. The Commission decided on 50% in-scope and 50% out of scope. This
will come up when the final mechanical claim comes to mediation or arbitration.
They agreed on this settlement so they could proceed to finish the work.
Mr. Hawley said the cost report is attached. It shows a remaining contingency
of $455,000, which includes assumptions regarding claim settlements, however
actual contingency determination needs to be based on audit and finalization
of the state reimbursement process
** MR. OPDAHL MOVED TO APPROVE THE ABOVE LISTED CHANGE ORDERS.
** MOTION PASSED UNANIMOUSLY.
3. Review and approve the following change order to DJ Contracting Inc. for additional abatement services at Brien McMahon:
CO #4 $4,274.00 Abate roof drains, marker boards, and
vibration cloth at Phase 3B areas
4. Refer the following to Common Council for approval:
“Authorize the Mayor, Richard A. Moccia, to execute an amendment to Special Testing Laboratories contract for additional materials testing and inspections at the Brien McMahon High School/Center for Global Studies project in the amount of $5,000.00. Acct. #0902/03/04 5010 5777 C0237.”
Mr. Hawley explained the project was originally established as a $130,000 budget, and they were authorized in increments so they could be monitored and checked. The first increment was $80,000, the second was $30,000, and the final increment will be for $5,000. The total will be $115,000 out of the original $130,000 budget.
5. Refer the following to Common Council for approval:
“Authorize the Mayor, Richard A. Moccia, to execute an amendment to Brook’s Laboratories contract for additional abatement monitoring and air quality testing at Brien McMahon High School/Center for Global Studies project in the amount of $59,535.00. Acct. #0902/03/04 5010 5777 C0237.”
Mr. Hawley explained that this was necessary abatement monitoring that was
required because the work was done while school was in progress. It is State
mandated and 34% reimbursable.
** MR. ARCARIO MOVED TO REVIEW AND APPROVE THE FOLLOWING CHANGE ORDER TO DJ
CONTRACTING FOR ADDITIONAL ABATEMENT SERVICES AT BRIEN MCMAHON:
CO #4 $4,274.00 Abate roof drains, marker boards, and
vibration cloth at Phase 3B areas
** MR. ARCARIO MOVED TO AUTHORIZE THE MAYOR, RICHARD A. MOCCIA, TO EXECUTE AN AMENDMENT TO SPECIAL TESTING LABORATORIES CONTRACT FOR ADDITIONAL MATERIALS TESTING AND INSPECTIONS AT THE BRIEN MCMAHON HIGH SCHOOL/CENTER FOR GLOBAL STUDIES PROJECT IN THE AMOUNT OF $5,000.00. ACCT. #0902/03/04 5010 5777 C0237.
** MR. ARCARIO MOVED TO AUTHORIZE THE MAYOR, RICHARD A. MOCCIA, TO EXECUTE AN AMENDMENT TO BROOK’S LABORATORIES CONTRACT FOR ADDITIONAL ABATEMENT MONITORING AND AIR QUALITY TESTING AT BRIEN MCMAHON HIGH SCHOOL/CENTER FOR GLOBAL STUDIES PROJECT IN THE AMOUNT OF $59,535.00. ACCT. #0902/03/04 5010 5777 C0237.
** MOTION PASSED UNANIMOUSLY.
B. Kendall Elementary School
1. Project update – by Amar Shamas (Program Manager)
Mr. Shamas said the administrative offices that were housed in the temporary trailers were moved back into the main building on June 24. The boiler room abatement work is completed, and the cafeteria and kitchen area abatement work is on-going. The construction will start in the next few weeks. The project is expected to be completed on time by the end of August.
2. Review and approve the following change orders:
COR #072 $ 9,145.00 Increase GMP Power wash and apply special paint to
building exterior at the B wing north
and west elevations.
COR #073 $ 3,296.00 Increase GMP Provide multimedia project and
associated equipment at the library per
FF&E design.
COR #074 $35,628.00 Increase GMP Provide and replace food servery
equipment at the library per A/E
design.
Mr. Shamas said COR #74 is included in the add alternates. There is $140,000
remaining and is shown on the cost report that is included.
** MR. HEMPSTEAD MOVED TO APPROVE THE ABOVE CHANGE ORDERS.
** MOTION PASSED UNANIMOUSLY.
3. Review only, changes approved by staff:
COR #071 $ 4,810.00 Increase GMP Provide cafeteria trash enclosure per
A/E sketch dated 5/21/06.
C. Norwalk High School
1. Project update – by Amar Shamas (Program Manager)
Mr. Shamas said they are still in the bidding process for the HVAC packages and the roofing packages. The construction work and abatement work has started. The tunnel work will start soon, and some demolition work has started. The administrative offices have been moved to Nathan Hale.
D. Tracey Elementary School
1. Project update – by Ben Burdsall (Program Manager)
Mr. Burdsall explained that since school let out, the furniture has been moved out into trailers, and construction is underway. The administrative offices are in the portables.
E. Columbus Elementary School
1. Project update – by Ben Burdsall (Program Manager)
Mr. Burdsall explained that this work is similar to the work at Tracey. The elevator was put in. Demolition work to the boiler room and the basement has started. The administrative staff has been moved off site to Brien McMahon High School for the summer.
F. Ponus Ridge and Nathan Hale Middle School
1. Project update – By Amar Shamas (Program Manager)
Mr. Shamas said that Silver Petrucelli is the architect for the project. Construction
manager proposals were received in late June, and the Commission will interview
them and hopefully have 1 construction manager for both projects ready to present
at the special meeting of the NFCC meeting on July 19.
SOUTH NORWALK LIBRARY
A. Project update by John Hawley – Program Manager
Mr. Hawley said that the AP Construction company is now finished with the project. The library staff is working on getting prepared for the opening, which is expected to be August or September. The change orders below are reflected in the previous cost report.
B. Construction Change Order (s):
1. Review and approve the following change orders:
PCO #67 $ 687.00 Increase GMP Added power feed for glycol
feeder tank.
PCO #68 $ 1,685.00 Increase GMP Add emergency ballasts to stair
#2 lighting required per code
PCO #69 $ 1,363.00 Increase GMP Build drywall enclosure at steel
bracing wall and duct in elevator
lobby
PCO #70 $ 185.00 Increase GMP Added blocking support at baby
changing station
PCO #71 $ 440.00 Increase GMP Infill old bookcase openings at
2nd floor room, behind fan coils
PCO #72 $ 3,757.00 Increase GMP Drywall and tape boiler room
ceiling per building code
requirement
PCO #73 $ 628.00 Increase GMP Frame a chase wall to cover old
brick at stair #2
PCO #74 $ 1,365.00 Increase GMP Added insulation at LL ceiling
to fill void per fire marshal
PCO #75 $ 127.00 Increase GMP Added soffit frame for clearance at
elevator door head
** MR. PACELLA MOVED TO APPROVE THE ABOVE CHANGE ORDERS.
** MOTION PASSED UNANIMOUSLY.
NATHANIEL ELY CENTER
A. Project update: By John Hawley – Program Manager
Mr. Hawley said the State has moved the approval date for this project from July 14 to August 18, due to other projects. The bid results will be presented at the special meeting of the NFCC on July 19. There was discussion about an advisory committee being formed. Mayor Moccia wished to advise the NEON group that they are to go through the NFCC and not the State or Federal agencies.
MISCELLANEOUS ITEMS
Mr. Hawley said that there will be a special meeting of the NFCC on July 19, 2006 to review/approve the Norwalk High School GMP and the Ponus Ridge/Nathan Hale construction manager.
Mayor Moccia mentioned that there has been discussion regarding the concession
stand at Brien McMahon High School being built by the Brien McMahon Father’s
Club in conjunction with the city and trade unions.
ADJOURNMENT
** MR. HEMPSTEAD MOVED TO ADJOURN.
** MOTION PASSED UNANIMOUSLY.
The meeting was adjourned at 6:20 p.m.
Respectfully submitted,
Carolyn Marr
Telesco Secretarial Services