Click To View Picture Tour
Click To View Picture Tour
NORWALK FACILITIES CONSTRUCTION COMMISSION ACTIONS

Click here for Minutes from Sept. 13, 2005


Facilities Audit & Analysis and Priority Needs Assessment (Final Draft)

Norwalk Facilities Construction Program


OCTOBER 6, 2005

ATTENDANCE: Alex Knopp, Stuart Wells; Bill Krummel; Steve Kerschner; Gregg Burnett (5:58 p.m.);
Stuart Opdahl (6:02 p.m.)

STAFF: John Hawley, Gilbane; Amar Shamas, Gilbane; Ben Burdsall, Gilbane, Alan Lo

OTHER: Ed Schmidt, Assistant to Mayor; Betsy Bain; Corey Nardonne, Silver/Petrucelli;

CALL TO ORDER

Mayor Knopp called the meeting to order at 5:36 p.m.

NORWALK SCHOOL PROJECTS

A. Roton Middle School

1. Project update by John Hawley (Program Manager)

Mr. Hawley introduced Mr. Ben Burdsall of Gilbane to present a review of the Roton Middle School renovation plan. Mr. Burdsall said the drawings, specifications and the cost estimate are complete. The project budget is being maintained. The drawings have to go to the State. He introduced Mr. Corey Nardonne of Silver Petrucelli Associates. Mr. Nardonne explained that there are new two-story connections between the existing buildings. They created new openings on the second floor. They increased the general accessibility requirements of the overall building. Windows, boilers, and the existing ceilings will be replaced. Abatement will be done on the flooring. The building will be completely outfitted with a sprinkler system. Fire alarms and emergency lighting throughout the school will be replaced. Handicapped parking spaces will be brought up to code, and further handicapped accessibility to the building will be provided. The three toilets on each floor in the back building will be upgraded to handicapped accessible. A science room from the back will be brought up front to create one entire science wing. This will be a sixth month construction project, to continue through next summer. The renovation of the science labs will be a model for other schools. If it becomes an add alternate, Mr. Burdsall said that the other three schools are in better shape than Roton Middle School. Mr. Krummel asked what “estimated construction costs, alternate IV” meant on the construction document estimate summary. Mr. Nardonne said it was the precast concrete. The masonry work is considered to be an alternate now, as it is a maintenance item, according to the State. It’s not part of the current estimate for the base bid work.

B. Brien McMahon High School/Center for Global Studies Improvement Project

1. Project update by John Hawley (Program Manager)

Mr. Hawley presented the Phasing Plan for Brien McMahon High School. It’s been under construction for two years as of this week. Phase II is under construction now. There has been $20M put in place over the last 7 months. Phase 3A is the other renovation that is underway now. It has a scheduled December 1 completion date. Phase 3B will start after the December break. They will move 80 classrooms and/or offices over the Christmas break. Ms. Bain asked about the December 1, 2005 occupancy date for the gym. Mr. Hawley said they are working towards getting into the gym for the start of basketball practice. Bleachers are scheduled to arrive on November 8.

3. Review only, change orders approved by staff:

CCA #20081 $4,693.00 Increase GMP Remove Jones water service to the main in Highland Ave
per SNEW
CCA #20114 $1,000.00 Increase GMP Steel revisions at wall in Rm 2050 per response to RFI #570
CCA #20160 $ 773.00 Increase GMP Add supports to black iron grid at auditorium ceiling penetrations
CCA #20168 $2,533.00 Increase GMP Revisions to the media center corner windows per FT details
CCA #20179 $4,116.00 Increase GMP Field revisions and downtime due to water main conflict at MH#22
CCA #20180 $2,040.00 Increase GMP Raise discovered sanitary cleanout to grade per RFI #627
CCA #20181 $1,000.00 Increase GMP Disconnect and reconnect kitchen kettle, swapped for different
model
CCA #20192 $2,330.00 Increase GMP Provide framing and EIFS to build soffit at door 1099 per FT
sketch
CCA #20220 $1,607.00 Increase GMP Remove existing lightpole and provide j-box at grade for paving

Mr. Hawley explained CCA#20081 was the capping of the water line on Highland Avenue.

C. Kendall Elementary School

1. Project Update by Amar Shamas (Program Manager)

Mr. Shamas said the project at Kendall is going well. November 23 is the new date to start the renovation of the ceiling of the 1st and 2nd grade wing.

D. Norwalk High School

1. Project update by Amar Shamas (Program Manager)

Mr. Shamas said Fletcher Thompson is still developing the construction documents, which are due December 2. They are targeting hazmat or abatement for early next month. On September 27, the Common Council approved the amendment for Nxegen for the cogeneration design. They will be submitting to CIAC for approval in the next week or so. Mr. Krummel said they had a good walkthrough of the facility today. He asked for an explanation of the Nxegen cogeneration proposal.

Mr. Burnett arrived at 5:58 p.m.

Mr. Shamas explained that the total project is $32.5M. The cogeneration incremental cost is estimated at $1.9M, and that includes all the work that was in the original plan.

Mr. Opdahl arrived at 6:02 p.m.

A. Roton Middle School

2. Review and approve the following action:

“Approve final plans and professional cost estimate for the Construction Documents phase at the Roton Middle School Extensions and Alterations Project No. 103-0232 E/A, Phase 1 of 1, and authorize filing Form EDO42, Request for Review of Final Plans with the State Department of Education.”

Mr. Hawley said that approval is needed by the Commission, it would then go to the Board of Education for approval this evening, and then to the State.

** MR. WELLS MOVED TO APPROVE FINAL PLANS AND PROFESSIONAL COST ESTIMATE FOR THE CONSTRUCTION DOCUMENTS PHASE AT THE ROTON MIDDLE SCHOOL EXTENSIONS AND ALTERATIONS PROJECT NO. 103-0232 E/A, PHASE 1 OF 1, AND AUTHORIZE FILING FORM EDO42, REQUEST FOR REVIEW OF FINAL PLANS WITH THE STATE DEPARTMENT OF EDUCATION.
** MOTION PASSED UNANIMOUSLY.

B. Brien McMahon High School/Center for Global Studies Improvement Project

2. Review and approve the following change orders:

BEA #167 $215,000.00 CM Contingency Final cost for premium time for PH 1 completion
(prior approval $75K)
CCA #20007 $ 22,461.00 Increase GMP Added foundations and steel to support AHU #13
per RFI #144
CCA #20015 $ 2,785.00 Increase GMP Provide drywall and column enclosure at field conditions
per FT
CCA #20069 $ 11,480.00 Increase GMP Provide fuel for temp boilers during Phase 1
CCA #20083 $ 5,861.00 Increase GMP Provide EIFS and exp joint at corridor #2058
per RFI #549
CCA #20097 $ 4,500.00 Increase GMP Provide power to auto shop fan and compressor
per RFI #564
CCA #20101 $ 6,432.00 Increase GMP Provide steel revisions at elev area and old café area
per RFI #555
CCA #20104 $ 5,600.00 Increase GMP Provide elec feeds to ACCU-5 and C-5 at stair 7
per RFI #569
CCA #20136 ($ 17,000.00) Decrease GMP Delete media center 2 layer drywall and alum reveals
CCA #20152 $ 18,830.00 Increase GMP Steel revs at boys/girls locker rms RFI’s 591, 609, 614,
619, 621, 623
CCA #20154 $ 2,040.00 Increase GMP Provide wall grilles/louvers in 4 computer rooms
per RFI #612
CCA #20161 $ 5,860.00 Increase GMP Provide EIFS and roof edges north of courtyard
per RFI #607
CCA #20164 $ 8,000.00 Increase GMP Provide ext wall and interior CMU at demolished
chimney, RFI #567
CCA #20173 $ 2,980.00 Increase GMP Provide framing and EIFS ceiling at vestibule 1281
per RFI #621
CCA #20178 $ 3,600.00 Increase GMP Provide TV (data & power) rough-in at 6 classrooms
per FT direction
CCA #20182 $ 7,334.00 Increase GMP Provide expansion at boys locker room roof per RFI #614 CCA #20183 $ 6,400.00 Increase GMP Provide wall infill at gym fans to be removed per RFI #624 CCA #30001 $ 7,100.00 Increase GMP Provide overhead elect sidecourt backstops in lieu of wall
mount
CCA #30003 $ 4,500.00 Increase GMP Install salvaged main court backstops in the auxiliary gym

** MR. OPDAHL MOVED TO APPROVE THE ABOVE LISTED CHANGE ORDERS.

Mr. Hawley said that BEA #167 for $215,000 came out of the CM Contingency. The final costs claimed by trades for premium time to complete the Phase 1 completion was over $300,000, due to overtime work, which was negotiated down to $215k. . This includes the original estimated $75,000, and is not in addition to. The consequences of not completing on time would have affected the operation of the school, and included substantial other increased costs such as extended leasing of the portables.

** MOTION PASSED UNANIMOUSLY.

C. Kendall Elementary School

2. Review and approve the following change orders:

COR #011 $1,496.47 Increase GMP Provide overflow roof drains at the addition per RFI #35
COR #012 $ 930.69 Increase GMP Demo existing sinks and cabinets in the B wing, RFI 40
COR #013 $1,563.63 Increase GMP Repair water leak inside the wall at the kindergarten classroom
COR #014 ($14,615.00) Decrease GMP Provide 2” duct wrap in lieu of outdoor insulation
COR #015 $1,022.06 Increase GMP Provide shaft wall enclosure for hot water breaching per RFI #12
COR #016 $3,748.84 Increase GMP Provide additional landscaping and ground cover at the island
located north of the parking lot

** MR. OPDAHL MOVED TO APPROVE THE ABOVE LISTED CHANGE ORDERS.

Mr. Burnett asked about the $14,615.00 credit. Mr. Shamas explained that it was part of the net credit for the ductwork located in the attic area.

** MOTION PASSED UNANIMOUSLY.

3. Review proposal from Silver/Petrucelli Associates to provide additional design services for millwork repairs/replacement and refer the following to the Common Council:

“Authorize the Mayor, Alex A. Knopp, to execute an amendment to Silver/Petrucelli + Associates design services contract for the Kendall Elementary School Project, for additional compensation for architectural services associated with classroom millwork repairs and replacement, for an amount not-to-exceed $15,400. Acct #09045010-5777-B0313.”

Mr. Shamas said this is the replacement of the existing millwork in the 1st and 2nd grade wings of Kendall Elementary School. The owner contingency is 12% spent. The CM contingency is 8-9% spent. Silver Petrucelli provided a proposal. The estimate was for $75,000 per wing.

** MR. OPDAHL MOVED TO AUTHORIZE THE MAYOR, ALEX A. KNOPP, TO EXECUTE AN AMENDMENT TO SILVER/PETRUCELLI + ASSOCIATES DESIGN SERVICES CONTRACT FOR THE KENDALL ELEMENTARY SCHOOL PROJECT, FOR ADDITIONAL COMPENSATION FOR ARCHITECTURAL SERVICES ASSOCIATED WITH CLASSROOM MILLWORK REPAIRS AND REPLACEMENTS, FOR AN AMOUNT NOT-TO-EXCEED $15,400. ACCT # 09045010-5777-BO313.”
** MOTION PASSED UNANIMOUSLY.

SOUTH NORWALK LIBRARY

A. Project update by John Hawley (Program Manager)

B. Review recommendation to award the balance of the Furniture, Fixtures, and Equipment bids and refer the following items to the Common Council for action:

“1a. Authorize the Purchasing Agent to issue a Purchase Order to Robert H. Lord Co., Inc of Manchester CT for the supply and installation of furniture at the South Norwalk Library Improvement Project for a total amount not to exceed $32,146.00. Account #09065621-5777-C0153.

1b. Authorize the NFCC to issue increases to the Purchase Order for a total not to exceed $3,200.00”.

2a. Authorize the Purchasing Agent to issue a Purchase Order to Insalco Corporation of Cheshire CT for the supply and installation of furniture at the South Norwalk Library Improvement Project for a total amount not to exceed $12,576.00. Account #09065621-5777-C0153.

2b. Authorize the NFCC to issue increases to the Purchase Order for a total not to exceed $1,300.00.”

** MR. KERSCHNER MOVED TO AUTHORIZE THE PURCHASING AGENT TO ISSUE A PURCHASE ORDER TO ROBERT H. LORD CO., INC OF MANCHESTER CT FOR THE SUPPLY AND INSTALLATION OF FURNITURE AT THE SOUTH NORWALK LIBRARY IMPROVEMENT PROJECT FOR A TOTAL NOT TO EXCEED $32,146.00. ACCOUNT #09065621-5777-C0153;
MR. KERSCHNER MOVED TO AUTHORIZE THE NFCC TO ISSUE INCREASES TO THE PURCHASE ORDER FOR A TOTAL NOT TO EXCEED $3,200.00;
MR. KERSCHNER MOVED TO AUTHORIZE THE PURCHASING AGENT TO ISSUE A PURCHASE ORDER TO INSALCO CORPORATION OF CHESHIRE CCT FOR THE SUPPLY AND INSTALLATION OF FURNITURE AT THE SOUTH NORWALK LIBRARY IMPROVEMENT PROJECT FOR A TOTAL AMOUNT NOT TO EXCEED $12,576.00. ACCOUNT #09065621-5777-C0153;
MR. KERSCHNER MOVED TO AUTHORIZE THE NFCC TO ISSUE INCREASES TO THE PURCHASE ORDER FOR A TOTAL NOT TO EXCEED $1,300.00.
** MOTION PASSED UNANIMOUSLY.

NEW POLICE STATION

A. Project Update – Alan Lo

B. Review DEP project closeout requirements and refer the following to the Common Council for approval:

“Authorize the Mayor, Alex A. Knopp, to execute any and all documents, [including, but not limited to, the filing of an Environmental Land Use Restriction (ELUR)] as required by the CT Department of Environmental Protection for the closeout of environmental site remediation at the New Police Station site.”

** MR. WELLS MOVED TO AUTHORIZE THE MAYOR, ALEX A. KNOPP, TO EXECUTE ANY AND ALL DOCUMENTS, [INCLUDING, BUT NOT LIMITED TO, THE FILING OF AN ENVIRONMENTAL LAND USE RESTRICTION (ELUR)] AS REQUIRED BYT THE CT DEPARTMENT OF ENVIRONMENTAL PROECTION FOR THE CLOSEOUT OF ENVIRONMENTAL SITE REMEDIATION AT THE NEW POLICE STATION SITE.
** MOTION PASSED UNANIMOUSLY.

C. Review only, change orders approved by staff:

PCO #183 $ 1,880.80 Increase GMP Control interface for RTU #1,3,5,& 6
PCO #196 $ 1,695.00 CM Contingency Replace damaged insulation
PCO#1187R $100,686.80 Decrease GMP Final adjustment on allowances
PCO #204 $ 2,804.64 Increase GMP Misc. flooring work
PCO #207 $ 5,484.96 CM Contingency Add’l work to set up control nece. for Commissioning
PCO #208 $ 7,917.69 Increase GMP Add’l equip. for IT/tele. during installation
PCO #209 $ 19,914.05 Increase GMP Add’l equip. for IT/tele. during installation
PCO #212 $ 1,365.46 Increase GMP Upgrade door closer

MINUTES OF PREVIOUS MEETING(S)

September 7, 2005

** MR. KERSCHNER MOVED TO APPROVE THE MINUTES OF SEPTEMBER 7, 2005.
** MOTION PASSED WITH THREE (3) ABSTENTIONS (BURNETT, KRUMMEL, OPDAHL).

Special Meeting September 13, 2005

** MR. OPDAHL MOVED TO APPROVE THE MINUTES OF THE SEPTEMBER 13, 2005 SPECIAL MEETING.

The correction to the minutes is as follows:

On page 4, 7th paragraph, 3rd sentence, it should read as follows:

If one fuel source fails, they can piggyback to the other fuel source.

** MOTION PASSED UNANIMOUSLY.

E. Tracey Elementary School
F. Columbus Elementary School

1. Project update by John Hawley (Program Manager)

Tracey & Columbus are proceeding at a parallel pace. Mr. Burdsall said both projects have been accepted by the State for review. They have commitment dates for late October for Columbus, and early November for Tracey. Mr. Krummel asked if there were any steps taken to look at alternative energy technologies in the schools. Mr. Burdsall said they hadn’t looked at alternative energies for these two schools, though energy efficiencies of all equipment specified were a focus. Mr. Hawley said that the timing of the new state law regarding alternative energies didn’t present itself correctly as the designs for these projects were already complete; but it will be applied to future projects.

NATHANIEL ELY CENTER

A. Project update by John Hawley (Program Manager)

Mr. Hawley said that the programming has moved along well. Ms. Linda Stone from Becker & Becker met with the staff and the programming phase is almost near completion. Ms. Mary Budrawich is the new Board of Ed staff person. Surveyors will start next week. Schematic designs are due in November. It will be a challenging project, because the center doesn’t close for the summer. The architects have visited Norwalk Community College to coordinate the Ely work with their program.

VOLK FIRE STATION AND THE FIRE SUPPORT SERVICES FACILITY

A. Project update by Amar Shamas (Program Manager)

Mr. Shamas said TLB architecture conducted several meetings last month and they completed the programming phase for both projects. The schematic designs are due in early November for both buildings. All environmental studies have been completed. The next step will be to hire a Construction Manager for this project. Both projects will be under one Construction Manager.

Mayor Knopp wants NFCC to consider an alternative energy resolution for future building construction projects. Mr. Krummel has drafted an initial resolution that Mayor Knopp proposes to be placed on the agenda for next month.

The next NFCC meeting is November 2, 2005.

** MR. WELLS MOVED TO ADJOURN.
** MOTION PASSED UNANIMOUSLY.

The meeting was adjourned at 6:42 p.m.

Respectfully submitted,


Carolyn Marr
Telesco Secretarial Services

 

CLICK HERE TO GO BACK ONE PAGE
CLICK HERE TO GO TO HOME PAGE